Superior lead line replacement project moves into its next phase in 2027
Superior will begin the next phase of its effort to replace every lead service line in the city in 2027, after about 230 lines in the mid-town area were replaced in the work done so far.
Photo: Superior Lead Line Replacement Project via Northland News Radio (KDAL)
The next phase of Superior's project to replace all of the lead service lines in the city will begin in 2027.
About 230 lead lines have been replaced so far in the city's mid-town area. That number is expected to double over the next year as work continues into additional neighborhoods.
The project is funded through the Wisconsin Department of Natural Resources, at no cost to eligible homeowners.
Mayor Jim Paine said the project is ahead of schedule and under budget. The city says it is committed to identifying and replacing all of the lead service lines as the work continues.
While customer-owned lines are being replaced, Superior Water, Light and Power and its contractors are also upgrading the utility's water distribution system by replacing utility-owned lead lines. That work is being done in coordination with the City of Superior and LHB contractors.